Tomorrow's Operational Brief

Tomorrow is won this afternoon.

Tomorrow's Mission

Supply

10,000 tonnes

Products

  • 20 mm
  • 10 mm
  • Roadbase

Build

2,000 tonnes of 20 mm

Operational Readiness

GO

READY WITH CONSTRAINTS

Operational Confidence

HIGH

Tomorrow's objectives remain achievable. Three operational constraints should be addressed before leaving today.

What's Stopping Tomorrow?

1

Fire Blast 74

Bench 4 access not yet graded for shot delivery

Due

Before 1600

Impact

Mining readiness

2

Grade Bench 4 Access

Contractor mobilisation pending confirmation

Due

Before 1700

Impact

Shot cycle continuity

3

Confirm Contractor Attendance

Weekend maintenance roster unconfirmed

Due

Before 1500

Impact

Plant continuity

Readiness Drivers

Mining

Healthy4 accepted shots

Plant

HealthyMain plant operational

Products

Watch20 mm, 2.4 days

People

HealthyFull crew

Spares

HealthyJaw liners available

Environment

HealthyNo issues reported

Safety

HealthyNo open actions

Actions Before You Leave